BURLINGTON POLICE STATION
BUILDING PROJECT
ABOUT
The Burlington Police Station has occupied this facility for over 30 years, originally built in the 1890s. Due to its outdated design, a feasibility study has determined that building a new police station on the existing site is the best course of action to meet current operational requirements and modern building codes.
Project Updates

Three Week Schedule View
Scheduled for the Week of June 29, 2026
-
Concrete foundation walls
-
Antenna foundation form work and placement
-
Structural CMU stairwells
-
Rough electrical for structural CMU building components
-
Foundation wall waterproofing and insulation
-
Backfill balance of highwall foundations
-
Install drainage structures
Scheduled for the Week of July 6, 2026
-
Antenna foundation form work and placement
-
Structural CMU stairwells
-
Rough electrical for structural CMU building components
-
Foundation wall waterproofing and insulation
-
Backfill balance of highwall foundations
-
Install drainage structures
-
Structural steel - upper level
-
Loading masonry materials to lower level
-
Install temporary power feed to building
-
Excavate for sallyport foundations
Scheduled for the Week of July 13, 2026
-
Structural steel - upper level
-
Loading masonry materials to lower level
-
Install temporary power feed to building
-
Excavate for sallyport foundations
-
Install sallyport concrete foundation